Analyses
are conducted by senior industry professionals that are recognized
experts in their field who can be called as expert witnesses.
DCR has been a lead analyst and expert witness on such notable
failures as the Geysers Unit 15 turbine failure and the Seminole
Electric twin 620 MW turbine failures at Palatka, FL. DCR also
determined the root cause failure and explosion of several transformers
at the Nugget Hydro Electric plant at Strawberry Valley, CA. DCR
not only identified the design problem within 24 hours but also
installed temporary equipment to allow the unit to be synchronized
moments before the power sales contract was to expire. |
|